Bent Tree Valley, Part 2: A Shop as a Rehearsal

Writer: Adam Witthauer
Adam Witthauer
9 minutes ago
8 min read

In my first installment in this series I laid out our dream of designing and building a house on 40 acres.  We began with a risk-centric look at the project as a whole, and how this approach was the only feasible way to get a truly custom home, on land I owned, without spending 7 figures.



Once I decided against a Barndominium, the shop became decoupled from the rest of the project.  This turned out to be a huge advantage.  The most important factor in risk management is having access to direct experience with whatever thing it is you are assessing.  The Army loves rehearsals too.  Ultimately, all Army training was some form of rehearsal.  Even the very simple stuff was there because it was something you might eventually need in combat, so you did it until you could do it perfectly without thinking about it. 


I read a book on DIY general contracting, and I had a good idea of how I wanted to break the work down.  I would contract the basic shop construction and concrete out, and do the driveway, electrical, and plumbing myself.  I contracted this in April 2020, early in the pandemic before lumber prices went crazy, and was actually able to get a significant discount by signing early.


With my initial plan in place I was ready to embrace the warmth of being thrown from the frying pan into the fire.  I was ready to fail fast, and excited to do it on a smaller project where I’d have time to lick my wounds and learn how to make fewer mistakes before committing to something that would be attached to a 30 year mortgage.


Pick Your Permit Strategy Deliberately

I won’t call this a mistake, and I can’t say I necessarily would have done all that much differently if I were to do it again, but I can certainly say this was an expensive lesson.  My county is infamous for being difficult to work with, particularly when it comes to zoning.  We are the first county that is truly outside of the KC metro when heading south in Kansas, and about 20-30 years ago there was enough southern sprawl that it looked like we were about to become part of the suburbs.  That growth slowed somewhat since then, but this idea structured a lot of how zoning and code is handled here. 



The character is primarily rural, but everything about the zoning process speaks to bracing for an influx of city folk.  When I got my application for building permit, it came with a ten page pamphlet that warned about how gravel roads are dusty, cows are smelly, and farmers drive their tractors on the highway.  Are you sure you want to build here?  I grew up 5 miles off pavement, so I just laughed and rolled my eyes.  I should have taken this as foreshadowing.


I had the choice of declaring the shop for agricultural use, or declaring it for some other purpose.  I didn’t have strong justification for ag use at that time, which would have exempted me from code inspection.  I didn’t have experience, and I knew that zoning folks would be crawling around quite a bit when it came time to build the house, so I opted to include every detail up front.  This cost me about 6 months of delays and $10k by the time all was said and done.


The kicker was my loft.  I had designed the shop to put all of its volume to use.  I needed a 14 foot tall door to get my bus inside, which meant a 16 foot eave height to give clearance to a conventional overhead garage door.  This height was also necessary to enable using a two-post lift without having to worry about overhead clearance.  My loft was inspired by the Quick Performance shop I worked at in college.  There was a loft over the general workshop area that had the lathe, press, parts washer, workbenches, sandblaster, etc.  This loft was where we kept a lot of our material stock, and was a super useful storage area.  With our dream house having a finished basement, this would be very useful to us. 



Root cause 1:  The loft

Framing the loft posed a serious problem though.  It required actual civil engineering design to meet code, and it had to meet code if I wanted to declare it under my building permit.  This is where 95% of my cost and schedule slip came from.  Yutzy’s pole barns were competitive because they didn’t incorporate custom things like designing and engineering a loft.  That change in scope would require re-negotiating the whole project, it would start more expensive, and I would also lose my 20% discount.  They suggested that they could add some footings to support the loft at a cost of about $300 in extra dirt work and concrete.  I could build the shop, close the permit, and would be all set up to build the loft whenever it was convenient to me. 


But I really wanted to do it “right,” so I hired an engineering firm to do the civil engineering design.  As a result, I had two drawings:  one for overall shop construction and one for all the framing inside the shop.  Having two drawings obviously wasn’t what I wanted to do.  One of the pitfalls of being persistent and solutions oriented is that you can get really far dug into a hole before you even think to stop and reconsider.  But hey, I got this far, so I reconciled that issue by including an affidavit on drawing precedence, defining which scope is applicable to which drawing, and what actions to take in the event of conflicts. 


Root cause 2:  “Not an Office”

The loft had a bathroom underneath, as well as an office, which served as a sort of clean room for manuals, a desk and computer, and a bench for precision work.  The office and bathroom would be the only areas with heat.  The first application was rejected due to concerns regarding the residential and/or commercial use of a room named “office.”  Surely this could have been resolved with a phone call or email documenting the clarification.  But if counties were inclined to operate with reason, they wouldn’t have the sparkling reputation they are known across the USA for. 


So I played their game.  I included a 7 page affidavit that declared that I am a married man with children, and we are not going to move into an 8x10 room with a bathroom, which is technically a ½ bathroom in that all it has is a toilet and a utility sink that isn’t even in the same room.  Also the plans clearly state that there is no septic in this phase of construction, no water connection, and no well, that the toilet and sink would only be stubbed-in, and that my family’s hygiene standards demand indoor plumbing.  I went on to describe that I had a job, and even if I were planning on running some unlicensed commerce out of this space, the last thing I would do is talk about it in a building permit application.  I also had every drawing revised to rename this room to “Not an Office.” 


The only response I received was “permit approved.”  I really hope that affidavit is sitting in a file somewhere, waiting to be seen by future generations.


Not pictured:  An office
Not pictured: An office

Delay is a cost driver

Every interaction with the county that didn’t result in an approved permit added about a month.  Before the “not an office” debacle there were a couple other questions about use of the space, who was doing the work, etc.  Getting the second set of engineered drawings added another 2 months total.  In all, getting all of this done “the right way” added a solid 6 months.  In exchange, I learned that expecting to reason with the county rationally was foolish, and not to invite trouble by putting anything more than needed on the permit.


Lesson learned:  Don’t put anything on the drawing besides the absolute bare minimum to get the county off your back.  Minimum habitability, then kindly get off my lawn.


I really should have heeded Yutzy’s advice.  The delay in final design approval did result in changes to the footings Yutzy was going to add.  This revision drove a re-quote.  The original quote was in April 2020, when lumber was in an unprecedented dip.  The requote was in something like August or September, after half of Colorado burned down, lumber doubled, and concrete was up something like 30%. 


The fun part:  Electrical

I went all in on electrical, it was fun, and it only affected the schedule by about a week.  My electrical strategy is, admittedly, entirely over-engineered.  Since this is a fully green field project, I needed everything up to the meter socket and mast for overhead connection.  Between the loft and electrical I’ve become quite familiar with IRC (the International Residential Code). 


The meter socket connects to a 200 amp main panel; it gets crazy after that almost immediately.  The meter socket is placed advantageously for overhead power connection, but most of the garage wiring is on the opposite end.  A little math told me it made sense to just run a 100 amp sub panel to the back of the shop, which I promptly filled to all but one socket.  If I want to expand, the 200 amp panel still has plenty of space. 


In addition to serving as the main service connection, I will be running two separate circuits to the house to manage main and generator power.  I looked up generator interconnects, and every other solution I saw looked more complicated and expensive.  Instead of a $2000 semi-automatic interconnect woven into every circuit and a $500 Bluetooth notification module, I opted for $200 for one additional panel; a separate emergency panel like in a hospital that gets connected to a manual interconnect. 


The electrical installation work I found even more rewarding.  I’ve always like metalwork, sheet metal forming, etc, so running conduit was immediately satisfying and rewarding.  Some people like to spend hours watching Netflix, I prefer spending that time turning $90 worth of EMT into functional art. 


When it came time for final code inspection, only two electrical discrepancies were noted:  1 for an additional ground wire from the meter socket to main panel ($8, 20 minute fix I was not going to argue about), and a request for an additional ground rod that I corrected the inspector on, which after further research he retracted. 


What the Rehearsal Bought

Six months and $10k is a real price, but I was happy to pay it on a project one-sixth the size of the house, with no 30-year mortgage attached. In exchange, I came away with a closed permit, a live electrical service, a working understanding of how our county operates, and a feel for how my own estimates drift when scope, materials, and approvals all move at once. No book could have taught me that, and the house needs every bit of it.

 

The Army closes every rehearsal with an after-action review: what went right, what went wrong, what we change. Consider this post mine. The shop is now the anchor point for everything else on the property, and its lessons feed directly into the house design. Next up: the orchard, which is more fun to talk about as winter sets in, and the design tools I used to turn years of ideas into a house plan.